Site Feasibility Study | Town of Lyons

download (3).jpeg

Lyons, CO

1 Acre

5,000 SF

Public Works & Parks and Rec. Department

Development Roadmapping

FEMA Funding

Following the devastating September 2013 flood, the Town of Lyons asked Trestle Strategy to research, evaluate, and recommend an appropriate location for a new Public Works and Parks & Recreation facility. Due to the challenging land constraints in this floodplain community, Trestle evaluated over 45 sites. The future site is to include a large office and workshop building, outdoor equipment storage, outdoor materials storage, and parking. The evaluation included infrastructure costs, overall cost estimates, site feasibility, and implementation scheduling.